Let’s illustrate the type of problems typical risk registers create and why the use of qualitative or scoring risk registers use should be avoided by management and not accepted by the Boards.

Imagine the company has 10 risks in its corporate or project risk register. Board wants to know how these 10 risks affect the objectives and to know the aggregate risk exposure.
Each risk exposure is usually calculated by multiplying probability and effect and then risks are summed to determine the aggregate risk exposure.

This, seemingly simple process, leads to very misleading and incorrect conclusions.

Let’s investigate a better way to measure risks. Risk 1 can occur with 20% probability. So, there are 2 possible scenarios: Risk 1 occurs (with probability 20%) and Risk 1 does not occur (with probability 80%).

If Risk 1 occurs the effect is 15$. If Risk 1 does not occur the effect is 0$. With the exception of some risks (market for example), there are no in-between cases, risk either happens or it doesn’t. The previous risk exposure Probability Х Effect = 3$ is totally misleading.

Here are the reasons:

Let’s compare the risk register above to a better alternative, still very simplified for the purposes of illustration only:

Because risks don’t occur on average, probabilities are better represented as Bernoulli distributions and they either occur or they don’t.

Effects are also uncertain and are best represented by another distribution, this time continuous, PERT just for illustration purposes. PERT has a minimum, most likely and maximum values. We used our original effect values as mode.

To calculate the total, we run a simulation.

The original sum of the risks was 160. We can now see sum of the risks is actually a range from 0 to 610.

In fact, there is 54% chance that the total risk for the year will be above original 160.

95% of the time (also sometimes called VaR) total risk exposure will be below 490.

Pretending that total risk is 160 is actually bad decision making and will mean risks most likely will not be mitigated properly and underfunded.

The above example is also not very realistic because it is assuming that every risk can only happen once per year.

For illustration purposes we replaced the distribution for the first 3 risks to occur more than once per year, it is now 1, 5 and 10 times per year accordingly.

This seemingly simple change in assumptions has a significant impact on the overall risk exposure.

When we compare a scenario where risks 1, 2 and 3 can occur multiple times per year, the risk exposure went from 0 to 610 to 17 to 3350 and the risk profile looks very different.

Pink in the diagram is a single risk per year, green is multiple risks 1,2 and 3.

The chance above original 160 risk exposure is now 100%. In fact, 95% of the time the risk exposure will be below 1919. Let that sink in, the risk exposure is 10X originally thought.

That is not the end, however. Previously we made the assumption that all risks are independent and are not correlated to one another. In reality, some risks may be codependent, and if one occurs, the other is more likely to occur as well.

Green in the diagram is the previous uncorrelated risk, the pink is the risk profile given correlation.

Given correlation, 95% of the time the risk exposure will be below 2440, that’s almost 500 higher than without correlation.

Now cast your mind back to the original risk total of 160, that’s 15X difference compared to a more accurate risk estimate. All we did was to use the better methodology.

That’s just the risk analysis part of the risk register, the mitigation, risk owner and other columns have as much issues if not more. The overall theme of the article is DO NOT use risk registers, but if you ever needed one, keep in mind:

Watch more on why we don’t need risk registers below:

Or download this case study as a guide: https://riskacademy.blog/download/risk-academy-guide-to-risk-registers/

Share your concerns about risk registers in the comments.